Please be advised that we have received the following from MassDOT regarding work to occur on Sumner Avenue next week as part of the "X" Reconstruction project. The proposed work will have a significant impact on traffic. The following is the notice received from MassDOT:
Project Construction Update
Lane Closures for Sumner Avenue Paving Starting Monday, September 14
What is Happening?
- The contractor will begin milling and paving operations on Sumner Avenue between Churchill Street and Dickinson Street, and at all adjacent local intersections.
What to Expect?
- Sumner Avenue will be reduced to one lane of traffic in each direction during work hours. Motorists should expect delays, reduce speed, and use caution when traveling through the area.
The work will require temporary turn restrictions to local streets and on-street parking limitations.
- Access to businesses, residences, and emergency services will be maintained during construction.
- The project team will coordinate directly with affected property owners and businesses as driveway reconstruction activities progress.
- Traffic control measures, including signage and police details, will be in place to guide motorists safely through the work zone.
When is this Work Happening?
- Work is scheduled to begin Monday, September 14, 2026.
- Construction activities are anticipated to occur for up to seven (7) working days.
- Work is scheduled on weekdays, Monday through Friday, from 7:00 a.m. to 3:00 p.m.
- This schedule is subject to change in the event of inclement weather and work hours are typical.
Stay Informed:
- Additional construction updates will be provided as the project advances.
- To reach the project hotline, please call: (413) 264-4240
- Project email: MassDOTSpringfieldX@dot.state.ma.us
- Follow FPCA on Facebook
Recent Posts

November 6, 2024
Have you seen the vibrant new mural that suddenly appeared on Lenox Street at the “X”? As you drive west on Sumner Avenue, your eye is drawn to the bright colors and images on your left. It’s yet another project installed by Common Wealth Murals (CWM) as part of the ongoing Portrait of a Graduate and Strategic Planning program that began five years ago.

November 5, 2024
Last summer, members of the FPCA Historic Committee began noticing the use of asphalt to patch sidewalks. We decided to walk the historic district to determine the extent of asphalt patching. We concluded that asphalt patching was “used everywhere” and that it was not in keeping with the desire to maintain an aesthetically pleasing and historically accurate neighborhood.